St-Jean
315-25kV Substation
Project description
The work on this project consists of the construction of a new control structure inside the existing substation. The growth in electricity demand in the sector is forcing Hydro-Québec to build this new building to meet growing needs.
The new station will be fed by a new line from the Sources station. The new 57 m x 32 m control building is constructed of steel framing on reinforced concrete walls and pilasters.
The work included the following:
- Excavation and backfill of the new building
- Formwork and concreting of foundations and interior slabs
- Mechanical, electrical and architectural works of the building
Characteristics
- Customer :
- Hydro-Québec
- Localisation :
- Dollard-des-Ormeaux, Québec
- Services :
- Construction of a control building and manoeuvring 315-25 kV
- Duration :
- April 2018 - January 2020
- Cost :
- 8 M$
- Project director :
- François Caron
- Project Manager :
- Pierre Murray