Description du projet

Several steps are to be carried out:

  • Replacement of supply channels and repair of walls
  • Rehabilitation of valves
  • Construction of a new control building
  • Reconstruction of an access bridge over the weir and overflow
  • Raising of embankment ridges and stabilization of certain sections
  • All mechanical and electrical work associated with these repairs

The work required maintaining pedestrian access and vehicle traffic throughout the duration of the project.

Caractéristiques
Client :
Parks and Infrastructures Canada - Maple Reinders/Demathieu and Bard
Localisation :
Trent Severn Waterway, Campbellford, Ontario
Services rendus :
Refurbishment of supply channels
Valve replacement
Associated mechanical and electrical works
Construction of a new building
Durée :
September 2019 to January 2022
Project Manager :
Nihad Terhzaz