Construction of generating stations – Rapides-des-Coeurs and Chute-Allard

Hydro-Quebec

Concreting penstocks, water intake and phase II Power Plant – Eastmain-1-A

James Bay Energy Society

Refurbishment of maneuvering area, Carillon Power Plant – Laurentides

Hydro-Quebec

Valves guides replacement, Carillon Dam – Laurentides

Hydro-Quebec

Iron mine project, phase II – Lac Bloom

CLIFFS Natural Resources

Construction Latchford Dam – North Bay, Ontario

Publics works and Canada Services

Refurbisment in 3 phases – Dubuc bridge, Saguenay

Ministry of Transport, Sustainable Mobility and Electrification

Construction of a permanent bridge – Romaine 2

Hydro-Quebec

Construction of the 315kV / 25kV transformer station – Wastewater treatment plant J.-R.-Marcotte

GE Canada

Installation of a generator group – North coast, Schefferville

Hydro-Quebec

Electric substation Bout-de-l’Ile – Montreal

Hydro-Quebec

Formwork and concreting water intake and spillway – Romaine 4

Hydro-Quebec